Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Data Center Zoning topic

No spam. Unsubscribe anytime.

Prospective data-mining facility to undergo two-step zoning review; safety and grid questions raised

2140887 · January 21, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

A company has applied for a data-mining operation in Jackson County. Staff described a two-step process: zoning commission review to identify appropriate district, followed by a board of adjustment hearing to set operating conditions. Supervisors also discussed fire and grid risks after a nearby facility fire in Grundy Center.

Jackson County supervisors were alerted on Jan. 21 that a proposed data-mining operation will follow the county’s two-step conditional-use process: an initial appearance before the zoning commission to identify an appropriate district, followed by a board of adjustment hearing to set special conditions for operation.

Laurie, a county staff member, said the application in question is from a different company than the one that previously spoke to the county; the new applicant submitted an application shortly after the county’s moratorium on such facilities was rescinded. She said Manchester has approved a site with roughly 50 server “boxcars” in a single industrial-park location — a scale the county has not routinely seen.

Supervisors and staff discussed safety and reliability concerns after a data center in Grundy Center caught fire. Laurie said county staff had spoken to Nick Schulte at Coconut Valley Electric Cooperative about the risk that a local fire could disrupt power to other consumers. “He says very slim because everything has like a circuit breaker…that facility's breaker is going to stop everything and it's not going to compromise the grid,” Laurie reported, paraphrasing the cooperative’s explanation.

The county will receive the data-mining application at the zoning commission and, if advanced, the project would next go to the board of adjustment where conditions such as fire-suppression, setbacks, and other operational limits could be imposed. No board-level approval or denial occurred at the Jan. 21 meeting.