Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Public Works Roads topic
No spam. Unsubscribe anytime.
Clay County approves final vouchers totaling $5.07 million for two mill‑and‑overlay projects
Summary
The board approved final contract vouchers for two road projects: SAP 014‑626‑032 (Knife River Materials) at $3,636,942.12 and SAP 014‑601‑8 (RJ Zavoral & Sons) at $1,437,053.47; one commissioner recused on the first item.
Get email alerts on the Public Works Roads topic
No spam. Unsubscribe anytime.
The Clay County Board of Commissioners approved final contract vouchers on Jan. 21 for two mill‑and‑overlay road projects that together total $5,073,995.59.
Justin Sorum, County Highway Engineer, presented the first final voucher for SAP 014‑626‑032, a mill‑and‑overlay project on Cassaw 26 that covered roughly 9.5 miles from Cassaw 19 to Trunk Highway 75. Knife River Materials was the contractor; the board approved a final payment of $3,636,942.12, lower than the original bid of $3,672,363.40. Commissioner Bair recused from that agenda item, as recorded in the meeting.
Commissioner Ebinger moved to approve the final voucher for SAP 014‑626‑032; Commissioner Kravanoff seconded and the motion carried by voice vote.
Sorum then presented the final voucher for SAP 014‑601‑8, the paving project on Cassaw 1 from Cassaw 20 to Cassaw 26, completed by RJ Zavoral & Sons. The board approved the final payment of $1,437,053.47; the original bid was $1,460,229.73. Commissioner Kravanoff moved approval and Commissioner Bair seconded; the motion passed by voice vote.
Board members praised the quality of the projects and noted the lower final amounts versus original bids. The county will record the approved final vouchers in its contract payment records and ensure recusals are noted where applicable.

