FDR Boulevard phases reach procurement milestones; county says construction work can start as permits and acquisitions clear
Summary
County staff told commissioners that phases 1A and 1B of the long-planned FDR Boulevard are near award or out to bid, while phase 1C was funded in FY2016. Land acquisition for later phases remains pending design completion and commissioners asked when traffic relief would occur.
St. Mary's County officials told commissioners on Nov. 10 that the multi-phase FDR Boulevard project has moved from planning into procurement for early segments, but full construction depends on permitting and property acquisition.
George Erickson, the county's CIP project manager, reported that phase 1A was about to be awarded, 1B was out to bid and that phase 1C received $3.8 million in FY2016 funding.…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat