Commissioners adjust public‑works CIP items: airport timing, remove some state signal projects, and move small sidewalk work forward
Summary
On the FY14–FY19 CIP staff review, commissioners agreed to shift airport projects rightward to match grant timing, remove several state signal projects from a county‑funded list after state/developer commitments, and move a small 100‑foot sidewalk connection and a Nicollet Park access design forward for earlier action.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
County public‑works staff walked the Board of County Commissioners through the transportation, marine and solid‑waste elements of the draft six‑year CIP on Feb. 25 and the board approved timing and scope adjustments for several projects.
Key outcomes: staff recommended — and the board accepted — shifting some airport design and construction items out one year (so the county match would be available if federal/state grants arrive later), keeping a park‑and‑ride/bus shelter project as a potential county backup if MTA grant funds are not awarded, and removing several state signal projects from the county’s FY2014 obligation list after the state or a developer assumed responsibility.
Why this matters: the decisions narrow the county’s near‑term cash commitments and preserve authority to accept grant funding if it materializes. On one signal project (Md 235/Loveville Road), state ownership determination removed the county’s cost share; another intersection project will be paid by the developer as part of APF/mitigation obligations, allowing the county to delete those line items from the FY2014 plan.
The board also heard public‑works staff say the Wildwood culvert and related utility relocations are slated for FY2014 and should proceed after utility work is complete. Commissioners instructed staff to move a small, 100‑foot sidewalk connection (Town Creek Drive to MD‑235, serving Bay Community Support Services) into FY2014 for quick completion. They also asked staff to begin outreach to the landowner for the Nicollet Park access connection and to consider advancing design into FY2014 if the landowner is cooperative.
Ending: staff will update the draft CIP to reflect the deletions and timing shifts and will include a short summary of the county’s reduced FY2014 cash needs and remaining contingent projects that depend on grant outcomes.