County highway department to advertise Feb. 17 bids for pipe, asphalt and CCMG overlays
Summary
Todd Howard asked commissioners for approval to advertise a Feb. 17 bid date for stone pipe, structure pipe, fuel and asphalt procurement and described planned bridge replacement and survey work; he also reported quotes pending for boiler chemical treatment at county facilities.
Get email alerts on the Highway Projects topic
No spam. Unsubscribe anytime.
Todd Howard, speaking for county highway operations, told commissioners the department plans to advertise bids on Feb. 17 for stone pipe, structure pipe, fuel and asphalt and to bundle some CCMG overlay work with other paving projects.
“We will advertise for bid dates February 17th, which will include stone pipes, structure pipe, fuel, and asphalt,” Howard said. He described combining CCMG project ccmg20.4-2 with other overlay and resurfacing work and said the department will follow the same approach used last year where appropriate.
Howard also described survey and inspection work related to a bridge scheduled for rebuilding this year. He said some local roads have load restrictions and one bridge requires a full replacement that the highway department intends to do in-house, adding that soil sampling and pile-driving tests are planned to verify alignment and foundation work.
Separately, Howard raised a facilities-maintenance matter: the county lacks a soft-water system at some buildings, and the highway/facilities team is gathering formal bids for chemical treatment and boiler-system maintenance, including a quoted annual cost and a one-time filter-install charge from a vendor. “This is for chemical treatment for the boiler system for any kind of scaling,” Howard said; he asked to return with a formal bid comparison.
Why it matters: the bid schedule and project sequencing set timelines for road and bridge work that affect local traffic and budgets; procurement and formal bids will determine contractor selection and project costs.
Provenance: Howard’s requests and project descriptions were presented during the public business portion of the meeting; the bid-advertising date and CCMG code were stated by Howard.