Council approves multiple water and sewer project change orders and pay applications

2138519 · January 22, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved a series of capital-project actions including a small change order and final pay application for a drainage repair project, payment approval for the water treatment plant progress (pay application 26), and a $60,825 change order for cathodic protection on the Sioux Falls force main plus related pay applications.

The Brandon City Council approved several water- and sewer-related contract actions and pay applications during the meeting.

Change order number 1 for the Big Suit drainage repair project was approved; staff reported the increase was just under $1,300 and reflected minor miscellaneous items such as landscaping around a lift station, moving plants, a manhole marker, and additional wattles requested by Game, Fish and Parks. The council approved the change order and a final pay application for that project.

The water treatment plant project advanced; council approved pay application number 26 as the project nears completion. Staff said mid-March was the target to have the plant running pending testing and equipment deliveries.

On the Sioux Falls force main project, the council approved a change order of $60,825 for cathodic protection work that staff described as a plan error (missed element in the plans). Staff said the contractor would have been paid for the work even if it had been included in the plans; the change order was approved after a roll call vote was recorded. Council also approved pay applications 5 through 7 related to that project.

Staff reported pipe boring is nearly complete; a number of obstructions were encountered, but the project is moving toward open-cut installation where needed. The actions were recorded as approved.