Pingree Grove approves large wastewater pay application; board hears timeline and cost details on well rehab

2137695 · January 22, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved pay application No. 15 for the wastewater treatment plant improvements for $2,540,459.25 and heard an update on well‑rehabilitation work, including a pump coupler delay and a $5,980 savings estimate if equipment is moved now rather than later.

The Pingree Grove Village Board approved pay application No. 15 for the wastewater treatment plant improvements project in the amount of $2,540,459.25 as part of the consent agenda on Jan. 21, 2025. Staff said the project is progressing, with electrical and HVAC work underway and digester structure work continuing.

The board also received a public‑works update on a well rehabilitation project. Staff reported that a pump/motor assembly pulled in November has had its motor sent to a Texas rebuilder and that completion has been delayed by a required coupler to join the motor shaft to the pump. A public‑works representative said the contractor estimated a $5,980 cost savings if village staff allow the contractor to move equipment from one well site to the other now rather than wait until fall; however, staff recommended caution about moving equipment before ensuring summer supplies would not be interrupted. The board indicated staff will return with a recommendation and timeline and will budget the work for the coming fiscal year if the board prefers to postpone until fall.

Why it matters: The approved pay application represents a significant cash‑flow milestone for the wastewater treatment plant improvement project. The well‑rehab discussion highlights operational risks if a backup well is not ready before peak demand months and tradeoffs between short‑term savings and reliability.

What happens next: Staff will report back with a timeline and a recommendation regarding whether to move equipment now (realizing the ~$5,980 savings) or budget the work for the fall to avoid possible summer service risk.