Lift-station parts delay and easement fixes slow Leitchfield bypass work; commission approves staff to correct easements
Summary
Commissioners heard updates that a bypass lift-station project is delayed while parts are expected early June, the gas-line project with DOT is proceeding slowly, and commissioners authorized staff and the city attorney to cure four to five defective easements and deduct the cost from the engineer’s fees.
Get email alerts on the Infrastructure Projects topic
No spam. Unsubscribe anytime.
Commissioners were told the lift station project on the bypass has finished pipe work but remains incomplete while crews await specialized pump parts now expected in the first part of June; staff said finish work likely will wait until spring.
The commission also heard that the gas-line project being coordinated with the Department of Transportation is progressing but slowly, with engineers and DOT exchanging questions about locations and easement issues.
Separately, staff reported four or five easements on the bypass route contain defects that the engineer and DOT have not cured. A staff member said he has exchanged multiple emails with Brandon Hamilton but that the problems remain unresolved. He asked for permission to have city staff or counsel correct the easements and deduct the time and cost from the engineer’s fee.
A motion was made and seconded to allow the city attorney to secure and correct the easements and to have staff (Dave) perform the work and deduct the cost from the engineer’s compensation. Commissioners voted to approve the action.
The commission also discussed contract timing and liquidated damages for the bypass contract, saying the city will work with the contractor on delays tied to material and equipment availability rather than immediately assessing liquidated damages.
There was no formal schedule change beyond the parts delivery estimate and the direction to proceed with curing easements and addressing contract-day issues cooperatively with the contractor.