Nueces County awards $22.7 million contract for Bob Hall Pier reconstruction

2127256 · January 17, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Commissioners approved a $22,710,869 construction contract with Callan Marine Limited for the long‑planned Bob Hall Pier reconstruction after value‑engineering reduced earlier cost estimates; court authorized staff to issue a notice to proceed subject to legal review.

Nueces County Commissioners Court voted June 18 to award a contractor agreement for reconstruction of the Bob Hall Pier to Callan Marine Limited for $22,710,869.

The decision follows a month of expedited value‑engineering work county officials said reduced the project cost without changing the pier’s designed public features. Coastal Parks staff recommended approval and the court authorized the county judge to sign the agreement subject to county attorney review. The motion passed unanimously.

County staff told the court the pier was being designed to high standards — “100‑year storm” structural criteria — and that the team preserved key top‑of‑pier features that officials said protect the structure from storm surge. Project managers said the work already included steps to seek further savings after contract award, including engineering changes that could substitute concrete for some steel elements.

County staff briefed the court on the procurement history and a June 14 value‑engineering summary that documented cost reductions. Commissioners instructed the program manager, LAN and the Coastal Parks director to meet with the contractor to issue a notice to proceed immediately after legal review.

The project is a major coastal infrastructure effort for Nueces County. County staff and the contractor will complete final contract and scheduling work before field mobilization begins.

Provenance: County packet material and staff presentation to the court supported the award; the court recorded the motion, second and vote on the contract at the June 18 meeting.