Commission permits relocation of visible conduit for previously installed solar at West Street property
Summary
A solar installer told the commission a crew had run visible conduit on the exterior rather than through the basement as approved; the commission approved remediation to relocate conduit into the basement and out of public view.
Get email alerts on the Solar Permit Remediation topic
No spam. Unsubscribe anytime.
The commission approved a remediation plan to conceal visible conduit and hardware for a solar installation after the install team ran conduit up the house instead of through the basement as originally described.
A representative identified as Zach from an installer said a miscommunication led to conduit placed on the exterior and visible from the public way. The proposed remediation is to reroute the conduit to the basement and run it to the rear of the house and then up into the attic, making the installation less visible. The installer said visible screw holes from previously mounted hardware would be patched and matched.
No members of the public spoke in opposition. Commissioners moved to accept the remediation as proposed and recorded an affirmative vote. Chair and commissioners asked the installer to follow the originally proposed route when feasible and to paint or otherwise minimize visible conduit if it cannot be fully concealed.
The commission’s approval is conditioned on completing the relocation to the basement and repairing visible exterior penetrations; the installer said they will restore wall finishes and submit photos or otherwise notify staff when remediation is complete.