Developer and restaurant reach staging, parking and delivery accommodations for Surnau project

6363536 · October 7, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff brokered an agreement between the Surnau Group and Tallulah restaurant to reduce construction impacts, including lane closures timing, temporary parking, valet options and trash scheduling.

City staff reported Oct. 6 that they facilitated a meeting between the Surnau Group (developer) and Tallulah restaurant to negotiate construction-staging impacts for the Surnau development site on Bates Street.

Under the arrangements summarized by staff: the developer will close a northbound lane on Bates between the alley and Maple only during daytime crane operations (roughly 7 a.m.–4 p.m.) but will reopen that lane in the evenings; the developer agreed not to use on-street parking immediately adjacent to Tallulah for construction vehicles; the Surnau Group offered two public parking spaces one block south on Bates for Tallulah deliveries and agreed to split costs with Tallulah for an evening/weekend valet that would use a nearby lot at 550 West Merrill (about 35 spaces); the developer also offered graphic design treatment for a construction screening wall visible from Tallulah’s deck; and Tallulah agreed to schedule trash pickups prior to 7 a.m. to avoid conflicts when the northbound lane is closed.

Staff said the group also agreed the Surnau Group would cover certain parking costs during construction; city staff noted historically the city has not charged for construction staging parking but that the fee schedule allows charging and commissioners asked staff to bring a policy item back to the commission for consideration.

No formal action was required at the commission meeting; the report summarized negotiated mitigation measures and staff next steps.