MMSD outlines three-phase plan to rebuild or replace 10 schools under $507M referendum
Summary
District staff described schedule and design work for the $507 million facilities referendum: three phases, two sites per year initially, construction expected to begin in 2026, and final occupancy targeted for school year 2029; public input sessions are planned for March.
District facilities staff briefed the operations work group on Jan. 13 about early design, site surveys and a three-phase construction schedule for the $507 million facilities referendum passed by voters in November.
Scott Chien (presenting as facilities lead) said the program covers 10 schools across three phases. Staff described a phased approach with two sites per year in the early phases and an increase to three sites in the final phase. Construction manager selection was underway (request-for-proposal evaluations and interviews had been completed) and architects are field-scanning…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat