Pueblo County approved a 1041 permit for Xcel Energy to build approximately 37 miles of 345 kV double‑circuit transmission line and related substation work in the northeastern portion of the county.
PUEBLO — The Pueblo County Board of County Commissioners approved a 1041 permit for Public Service Company of Colorado (Xcel Energy) to construct segments of Colorado’s Power Pathways transmission line that cross unincorporated Pueblo County.
The application, heard as case SLI‑24‑5, covers roughly 37 miles of new 345‑kilovolt double‑circuit transmission line in Pueblo County, with the record showing approximately 26 miles for segment 4 and 11 miles for segment 5 in the county. The proposal also includes equipment additions at the existing Tundra Substation and a new Sandstone Substation east of Boone Road and south of County Road 622.
County staff reopened a hearing continued from Dec. 12 so the applicant and staff could agree revised…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat