Staff reports 60% facility submittal review, reservoir mixer fault and maintenance shortfalls
2112675 · January 14, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.
Summary
Public Works staff said the facilities rehabilitation 60% submittal is under review, the orchard reservoir mixer installed recently is not functioning and the distribution crew fell short of some preventative maintenance targets due to staffing and PTO changes.
Public Works staff updated the Board that the 60% plant design submittal for the facilities rehabilitation project is under in-house review and that early indications show costs similar to the 30% submittal. Staff said reviewers will meet the consultant to consolidate comments and that now is the time to make…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans