City staff reported progress on permit processing after hurricanes Helene and Milton, announced they have waived about $1.7 million in permit fees and recommended extending the waiver program to April 22, 2025. Commissioners gave staff consensus to proceed; a formal resolution will return to the next meeting.
Get email alerts on the Recovery Permits And Fees topic
No spam. Unsubscribe anytime.
St. Pete Beach officials reported continued progress on post-hurricane recovery permitting at the Jan. 14 commission meeting, and commissioners gave staff consensus to extend waiver and refund policies for hurricane-related permit and plan-examination fees through April 22, 2025.
Community Development Director Denise Sanderson told the commission the department has issued 1,256 permits (about 300 closed) since the recovery effort began and has waived or refunded roughly $1.7 million in permit and review fees so far. Staff also reported $523,000 in revenues from pre-hurricane permits that were processed during recovery work; those revenues are expected to level off.
Why it matters: The city established a $2 million building fund reserve minimum in November and is billing many vendor and contractor hours to state mission requests; Sanderson warned that significant out-of-pocket expenses will hit the city in April as state-funded contract support winds down and demolition and rebuilding activity increases.
Key updates from staff: Sanderson said the city is using four vendors to process assessments and permit-review packages after the disasters and has improved SISD (substantial-improvement / substantial-damage) review approvals from roughly 30% to under 50% approval for initial packages. She described data-quality issues from the county-authorized vendor (duplicates and misaligned columns in transfers) that have caused staff to spend extra time cleaning files before issuing letters. The city said it is sending 0% flood-damage letters to properties with ground elevations above 7.2 NAVD based on county GIS data to reduce unnecessary appeals.
Appeals and documentation: Sanderson said appeals will allow applicants to challenge both the damage-determination and the computed damage percentage; final letters will remain attached to property records. The department emphasized preparing audit-ready files — “we can expect an audit in 1 to 3 years” — and has called for volunteers and paid mission support to help owner-builders and elderly residents complete paperwork.
Fee-waiver extension: Sanderson recommended extending the permit-and-plan-review fee waivers until April 22, 2025. The commission signaled consensus to move forward with that extension; staff will bring a documenting resolution to the next meeting and said the waiver is effective immediately.
Staffing and service levels: The city is relying heavily on contract plans examiners, inspectors and permit technicians; staff reported next-day inspection continues. Sanderson said the city hopes to maintain enough contract staff for several months but cautioned that vendor personnel availability has been uneven; managers are actively managing contracts and replacing nonperforming hires.
Other recovery notes: Sanderson said 30 local historic-designation applications have been filed (26 approved) and commercial debris noncompliance has been reduced to eight properties; the city intends to pursue cost recovery where it must pick up noncompliant commercial debris. She also noted state-led programs such as Elevate Florida are preparing federal grant portals that homeowners may be able to use later.
Ending: Commissioners asked staff to prioritize volunteer outreach and a “lobby ambassadorship” so elderly and digitally disconnected residents can get help filing permits. Staff said it had coordinated communications to neighborhoods and planned to post updated dashboards and data on the city website within 24 hours of the meeting.