Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Solar Projects topic

No spam. Unsubscribe anytime.

Woodstock CUSD 200 board approves smaller solar installation, directs staff to pursue added capacity if utility approves

2111769 · January 15, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Woodstock Community Unit School District 200 Board of Education on Oct. 12 voted to authorize a contract change order to build a 590-kilowatt solar array, approving a not-to-exceed cost of $1,400,000 and directing the administration to keep pursuing approval from ComEd to expand the system if possible.

The Woodstock Community Unit School District 200 Board of Education on Oct. 12 voted to authorize a contract change order to build a 590-kilowatt solar array, approving a not-to-exceed cost of $1,400,000 and directing the administration to keep pursuing approval from ComEd to expand the system if possible.

The vote followed extended discussion about earlier engineering work, costs the district has already incurred and uncertainty about utility interconnection approvals and available incentives. The board first considered a separate motion to proceed with a larger, roughly 953-kilowatt system tied to a contractor’s package; that motion failed, and a subsequent motion to limit the scope to the 590-kilowatt system passed.

Board members and staff raised three recurring points during the debate: (1) ComEd has restricted the amount of capacity the district can interconnect at some sites, which forced the district to revise earlier plans; (2) the district has already spent money on engineering and application work (speakers cited amounts ranging from about $200,000 to as much as $300,000); and (3) additional incentives and rebates — including Illinois program incentives and ComEd inverter rebates and federal tax credits referenced during the meeting — are expected but not guaranteed.

District staff explained the district’s original bid package included two components (a larger ~1,460-kW piece and a ~590-kW piece); ComEd approved the smaller component and denied the larger one because of grid capacity constraints. The district still has an outstanding application for additional capacity (several hundred kilowatts) that staff said remains under technical review by ComEd and may require extra information before approval.

Under the approved change order the superintendent is authorized to execute a contract amendment with the district’s contractor (motion text referenced “All Tough Industries” in the meeting record) to build only the 590-kilowatt portion. Board members who opposed the larger option said they were concerned about sinking additional money into a configuration that ComEd might not approve; board members who supported a larger build cited the money already spent on engineering and the potential long-term energy savings and incentives.

The board also instructed the administration to continue efforts to secure ComEd approval for the additional capacity (described in the meeting as roughly 360–406 kilowatts) and to report back if that approval is obtained; staff said the district’s existing application remains active and that, if ComEd approves the additional capacity, the board could consider expanding the system later. Staff also noted a ComEd rule referenced in the meeting: approved interconnection space can be lost if not used within one year of approval.

Votes at a glance: • Change order to limit contract to a 590-kilowatt system, not to exceed $1,400,000 — approved (see action record below). The board also asked administration to continue pursuing approval for additional capacity to expand toward roughly 943 kilowatts if ComEd grants interconnection. • 2025–26 fee schedule — approved by roll call (see action record below).

Background: The solar project has been discussed at prior meetings, including a December meeting referenced by board members, where a larger system configuration was originally considered. District staff said the project timeline and size have been driven by ComEd interconnection responses that arrived after bids and engineering were submitted. Staff cautioned that incentive estimates (rebates, tax credits, Illinois programs) are contingent on program availability and final approvals.

The board did not adopt any additional budget appropriation at the meeting; the approved change order amends the existing contract and was accompanied by board direction to monitor and pursue additional approvals if they become available.