Staff reports $170,000 change order for West Pasco Water Treatment Plant Phase 2; project remains below original estimate

2111577 · January 15, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff presented Change Order No. 12 for the West Pasco Water Treatment Plant Phase 2 project, a $170,000 package covering as-built verification, a noncompliant clear-well overflow retrofit, making a temporary generator connection permanent, and dewatering work. Staff said the overall project cost remains below the original engineer estimate.

City staff presented Change Order No. 12 for the West Pasco Water Treatment Plant Phase 2 project, a package valued at roughly $170,000 covering multiple items the contractor must perform.

The four primary elements in the change order are: field verification of infrastructure locations in the intake facility to allow installation of seismic restraints; correction of a noncompliant clear-well overflow air gap to prevent treated-water contamination; making a temporarily installed generator connection permanent to ensure reliable service; and dewatering a wet well so constrained-space work can occur that exceeds city staff capacity. Staff said the city initially expected to handle some tasks in-house but determined certain items required contractor work.

Maria Sarah told the council the overall project is an approximately $11 million undertaking with an engineer’s estimate of about $13 million; despite multiple change orders, staff said the project remains below the original estimate. Staff said the work is funded largely through a low-interest loan from the state Department of Health and that the Department has approved incorporating the change order into the loan costs. No council vote on the change order was recorded in the transcript; staff said approval will be brought forward in the regular contract-change process.