Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Wastewater Project topic

No spam. Unsubscribe anytime.

Board approves $187,202 in change orders for wastewater update project; staff expects a $60,000 offset

2111548 · January 14, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Two change orders totaling $187,202 were approved for the wastewater update project. Staff said the larger change order covers a relocated flame arrestor and additional monitoring devices; a $60,000 in-house cleaning credit will reduce net project cost.

The Port Washington Board of Public Works approved two construction change orders for the city’s wastewater update project totaling $53,907 and $133,295. Staff described the work as necessary corrections and safety-related additions discovered as the project progressed.

Dan, a wastewater staff member, told the board the $53,907 change order includes 11 smaller items — such as concrete grout repairs for a discovered crack after protective coating removal — and that seven of those items had already been completed to keep crews productive. Dan said those items were reviewed by the project engineer and judged reasonable.

The larger $133,295 change order focuses on work around the digester portion of the project. Dan said the city must relocate a flame arrestor outside the building, which requires excavation, a containment concrete structure and installation of a gas line. He also said roughly $40,000 of the amount relates to two cover-monitoring devices that were not identified during initial assessments of 35-year-old components.

Staff noted the project team expects to perform cleaning of a sludge-storage tank with in-house personnel and a contractor during a later phase, which will yield a roughly $60,000 credit to the project. The board’s approval authorizes the change orders to proceed and instructs staff to issue the change-order paperwork to the contractor, August Winters & Sons.

Cam moved and Alderman Gasper seconded the motion; it carried by voice vote.

Staff said a project contingency of roughly $550,000 remains for the overall $12 million project, and that contingencies and engineering oversight reduce the risk of cost surprises going forward.