Burleson ISD board approves $7.36 million guaranteed maximum price for Mound Elementary gym; several procedural measures passed

2111476 · January 14, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Burleson ISD Board of Trustees approved a $7,356,604 guaranteed maximum price for a new gym/storm-shelter at Mound Elementary and passed several routine measures, including temporary hiring authority for the board president and pay for staff during a recent district closure.

The Burleson Independent School District Board of Trustees voted Jan. 13 to approve a guaranteed maximum price (GMP) of $7,356,604 for a new gymnasium and storm shelter at Mound Elementary and approved several related and procedural items.

The GMP covers construction contract costs presented by Jackson Construction and includes contractor markups, general conditions, bonds and insurance. Brian Parma of Jackson Construction summarized the recommendation: “What we are bringing to you tonight for a GMP recommendation is the $7,356,604.” The district previously procured long-lead electrical equipment in 2022 that will be used for the project and that procurement cost $431,000, staff said.

Why it matters: Mound Elementary did not have a conventional indoor gym with a permanent court; the new facility is designed to serve as both a full gym and a storm shelter for the school’s occupancy. District staff and project architects said design adjustments reduced the amount of glass to meet shelter requirements while keeping the building’s planned architectural expression and material palette to match the existing campus.

Staff and contractors described remaining scope items and owner-held allowances that are excluded from the GMP (data cabling, audio-visual, intercom and security work will be completed by the district). Plueger Architects noted that the project maintains a secure indoor connection between the existing school and the new gym/storm shelter.

Votes at a glance

- Approve guaranteed maximum price (GMP) for Mound Elementary project as presented — outcome: approved. - Grant board president authority to approve new hires between Jan. 13 and the next regular meeting in February, with ratification of hires at the February meeting — outcome: approved (motion carried). - Approve resolution to pay employees for days the district was closed due to the recent storm — outcome: approved. - Approve consent agenda as presented — outcome: approved.

Board members who spoke during the item thanked the facilities committee and district staff for work on the multi-year project and noted the district expects site activity to begin in early February. Several campus staff representatives who addressed the board expressed appreciation for the approval and described the project as “desperately needed.”

Background and timeline: District staff said parts of the project procurement began in 2022 and the overall project has been under discussion for roughly two years. The board’s facilities committee reviewed the GMP in detail before the full board vote.

Next steps: District staff and the general contractor said they expected to begin visible site work in the first week of February, pending routine preconstruction activities.

Ending: The board’s approval authorizes the district to move forward with the construction contract at the GMP amount and to begin the construction phase, subject to standard contract execution and mobilization steps.