Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Water Infrastructure topic

No spam. Unsubscribe anytime.

Brookfield approves change orders for lead service replacements; IEPA loan authorization discussed

2111363 · January 15, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Trustees approved four change‑order resolutions tied to the village’s 2024 water‑service replacement and water‑main projects. Staff said additional lead services were discovered in the field, IEPA authorized roughly $700,000 in loan funding at 0% interest, and the village will use contingency funding to cover remaining costs.

The Brookfield Village Board on Jan. 13 approved multiple change orders tied to the village’s 2024 water service replacement program after staff reported contractors found additional lead service connections during excavation.

Village Engineer Derek Triclar told trustees crews discovered previously unidentified lead service connections when crews opened typical 7‑by‑7 pits; some services that appeared to be copper inside homes were later found to transition to lead in the public service. Staff said roughly 3 percent of visually identified copper services checked in the field turned out to have lead components.

To address the extra work, trustees approved change orders for multiple project phases: a phase‑1 change order (amount not specified aloud in the meeting record but described in staff backup), phase‑2 change order to 5 Star Energy Services LLC for $359,605, phase‑3 change order to 5 Star Energy Services LLC for $266,300, and a change order for the 2024 Water Main Improvements project to Suburban General Construction, Inc. for $150,500.

Triclar told the board the Illinois Environmental Protection Agency has authorized approximately $700,000 in additional funding in the form of a 0% interest loan to cover the extra replacements; the village’s loan includes a 3% contingency. Staff said the approach taken—bundling projected additional services into the change orders—helps keep the original contractor pricing and avoids re‑bidding. Trustees approved each resolution by roll call.

Staff said about 100 more services remain projected for the year and that the change‑order quantities were projected to the end of the project rather than reflecting only the work completed to date.

Ending: The resolutions authorize the contractor work and financial adjustments; staff said they will pursue IEPA funding and contingency reimbursement to limit the village’s net cost.