Planning Board authorizes partial release of Marion Way performance surety, withhold tree/sidewalk amounts
Summary
The board authorized staff to issue a partial performance surety release for the Marion Way subdivision but directed that funds be withheld for incomplete sidewalk and street tree work.
Get email alerts on the Performance Surety topic
No spam. Unsubscribe anytime.
The Planning Board authorized staff to issue a partial release of the performance surety for infrastructure work at the Marion Way subdivision while withholding enough funds to cover incomplete sidewalks and street-tree planting.
Why it matters: Releasing a portion of a performance surety signals completion of major infrastructure work while preserving funds to ensure remaining tasks โ notably sidewalk construction and planting โ are finished to specifications.
What staff reported: Planning staff said final coats of paving and curbing around the retention pond are complete. Outstanding tasks include the sidewalk near Union Street and street-tree plantings; the trees likely cannot be installed until spring. Staff estimated the withheld amount for street trees to be in the range of $10,000โ$12,000 and said final estimates are in office files.
Board action: The board voted to authorize staff to process a partial release, withholding funds to cover the sidewalks and street-tree work until inspection. The motion directed staff to prepare the partial release and to hold the withheld funds until the inspected work is complete.
Next steps: Staff will return the partial-release paperwork after reserving the agreed withholding; sidewalk inspection will be required before the withheld funds are released to the developer.