Daviess County officials hear courthouse renovation progress; substantial completion set for April 17
Summary
Contract representatives told commissioners the courthouse renovation is in finishing phases on all three floors, with a substantial completion date of April 17 and a construction contingency of $197,000; commissioners asked for renderings to hide a large rooftop HVAC unit and were invited to an on-site inspection.
Daviess County commissioners received a construction progress update on the courthouse renovation, which project staff said is in finishing phases across all three floors and remains on track for a substantial completion date of April 17.
Project staff member Derek said the third floor has begun flooring prep and light-fixture installation, the second floor is wrapping paint…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat