District project update: turf fields, intercom shipping delays, kiln electrical change order expected

2110105 · January 14, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff gave a progress update on projects funded by the April bond: turf supplier approvals, site work contracts, construction on school additions, sidewalk bids, intercom shipping delays, fine-arts room remodels and an upcoming kiln electrical change order.

A district staff member provided a status update on multiple projects funded by the April bond, reporting progress on athletic fields, school additions, road and sidewalk work, intercom installations, fine-arts upgrades and HVAC planning.

The presenter said ATG was approved as the turf supplier and Mid America Golf was approved for the site work; soil samples and core testing are underway at the fields and some site work was paused by weather but expected to proceed on schedule. The Hozia addition was described as making “good progress” and tied into the existing building; the presenter said the project should be complete by early April as planned.

Road work at Carden Park had started before break and was continuing more slowly while weather conditions persist. Sidewalk work on Pickett Parkway is out for bid after a pre-bid meeting produced a strong contractor turnout. Oak Grove was scheduled for a site walkthrough to start design work with Goldburn and work there would begin once school is out in June.

Intercom system installation was delayed by shipping problems but wiring started in some buildings; Parkway and Pickett were identified as the first schools to receive full installation once materials arrive. Fine-arts spaces saw work over the break: middle-school risers removed, new paint and carpet installed in band rooms, and auditorium carpet and paint ordered. The presenter said a change order would be brought to the board to support electrical upgrades for kiln installations because existing electrical boxes were undersized for the kiln loads.

On HVAC, the presenter cautioned that bond funding alone will not cover replacing Daikin units at all buildings and said district staff are evaluating where to prioritize bond dollars, in-house work and potential CIP funds for next year. Science, technology and STEM resources deliveries were reported as underway, with professional development planned to put materials into classrooms.

No formal board action was taken on these updates; the presenter said the district would return with a change order for the kiln electrical work at an upcoming meeting.