Council accepts Savage Sewer Replacement Phase 1, final cost $977,054

2110005 · January 7, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Show Low accepted completion of the Savage Sewer Replacement Phase 1 project by Apache Underground & Excavating LLC with a final project cost of $977,054 and approved a scope revision of $53,018; staff recommended release of retainage and start of a two-year warranty period.

Show Low City Council accepted the Savage Sewer Replacement Phase 1 as complete and approved related contract closeout actions at the meeting.

Staff reported the construction contract had been awarded on Sept. 3, 2024, to Apache Underground & Excavating LLC for $924,036. The work included removing the existing sewer main and installing approximately 25,100 linear feet (reported in staff remarks as 25,100 linear feet) of new 18-inch SDR 35 PVC sewer main, installation of nine polymer sewer manholes, sewer services and replacement of asphalt and concrete removed for the work. The project was partially funded by a congressional district spending grant that allowed up to $800,000 with a required 20% city match.

Because the low bid was about $925,000, staff identified additional scope to use more of the grant funds. The final project cost is $977,054, leaving a scope provision (net increase) of $53,018. Staff recommended accepting the project, approving the $53,018 scope revision, releasing retainage and initiating the two-year warranty. Councilman Hackett moved to accept the project at the final cost and approve the scope revision; Councilman Adams seconded. The motion passed unanimously.

Staff said any grant-eligible share of the $53,018 will be paid from the grant (80%), and the city's match will be covered by existing budget line items for the project. The council approved release of retainage and the start of the two-year warranty period.