District outlines bond project delivery schedule; staff warns pre-bond design fees could be multi-six-figures
Summary
Facilities staff presented a project delivery schedule tied to a potential April bond, estimating a roughly nine-month design window for major projects and warning that pre-bond design or preconstruction services could reach multi-six-figure costs.
Facilities staff outlined a project delivery schedule for bond-funded work and described steps the district would take if voters approve a bond in April.
"We're always shooting for a summer" move-in, Mr. Garel, a facilities staff member, said in a high-level timeline for major projects. He described a three-phase design process for large projects: schematic design (~2 months), design development (~3 months) and construction documents (about 3+ months), and said those phases could total…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat