$23.5 million bond update: roofs underway, cameras and West Senior parking reconfiguration headed for SED review
Summary
Young and Wright Architects told the board that phase 1 of the $23.5 million capital-improvement program — $15 million for roof replacements — is underway and that phase 2, budgeted at $8.5 million, has been submitted for SED review and includes elementary security cameras and a possible West Senior parking reconfiguration.
Young and Wright Architects representatives updated the board on the 2023 capital improvement project, saying the overall project budget is $23.5 million and detailing work on roofs, security cameras and a potential West Senior parking reconfiguration.
Marissa, a Young and Wright project coordinator, said phase 1 has a $15 million budget and includes roof replacements at Northwood Elementary, West Senior and East Senior. "Construction started last summer, and we got about halfway through," she said, adding that crews will return in spring and the district…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat