Titan Activities Complex: baseball progresses, tennis delayed after irrigation damage; district, contractor negotiate repairs
Summary
Work at the Titan Activities Complex has advanced on the baseball field while tennis court work paused after an electrical contractor struck an irrigation pipe and flooded part of the court base; district and contractor are negotiating responsibility for replacement fill material.
Get email alerts on the Facilities Construction topic
No spam. Unsubscribe anytime.
District administrators told the board that construction at the Titan Activities Complex has visible progress on the baseball field but that tennis court completion is delayed after an irrigation pipe was damaged during electrical work.
Site observations show dugouts and field work near completion on the baseball side. On the tennis pad, crews hit a three-inch irrigation pipe while installing electrical lines for lights; the pipe breach was not noticed while irrigation was off during initial grading. When irrigation was turned back on, the leak saturated a section of the court pad and the treated soil was compromised.
Dr. Joel Bollinger told the board the district met with the electric contractor, the subcontractor and project managers to clarify repair costs and responsibility. The district maintains the work must be corrected before completion, but the parties have not reached agreement about who will pay for replacement fill, compaction and any necessary soil treatment. Dr. Bollinger said the district has "okayed for the work to move forward" but acknowledged the schedule will be tight to meet season targets.
The board also received an update on hail damage from a September storm. The district has submitted estimates for shingle roof repairs and is awaiting additional estimates for HVAC work; insurance adjuster contacts are coordinating sample decisions and potential upgrades, including converting some shingle roofs to metal where cost thresholds allow.
Why it matters: The Titan Complex supports multiple extracurricular programs (baseball, tennis and fundraising-driven concession improvements) and schedule slippage could affect spring athletics and facility openings. Responsibility for the repair costs — whether covered by the contractor, subcontractor or absorbed against contract retainage — will affect project accounting and timeline.
Next steps: Administration will continue negotiations with the contractor and subcontractors, proceed with approved repair work where feasible, and keep the board updated about schedule implications and cost responsibility.