Bennett Building renovation substantially complete; elevator work and final pay remain
Summary
County staff reported the Bennett Building project reached substantial completion and a final pay application was submitted in December. Three elevator replacements remain the primary barrier to occupancy; staff said two crews are working and estimated elevator completion in April.
Carla of Bailey Edward Design reported that the county plaza renovation—now referred to as the Bennett Building—reached substantial completion earlier in 2024 and that the contractor submitted a final pay application to the county in December.
The update matters because the facility cannot be occupied until the elevator work is finished. County staff said three elevators are being replaced: the north elevator (intended for staff use) is essentially complete but the emergency phone has not been installed; two south elevators intended for public use are still under construction.…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat