Edgewood renovation advances; phase 2 bid packages presented to committee
Summary
Administrators reported near-completion on Edgewood phase 1 exterior work and presented phase 2 bid results and proposed second-shift schedule for interior work; concerns were raised about weather delays, lead times for auditorium seating and potential undiscovered asbestos.
Get email alerts on the Facilities Construction topic
No spam. Unsubscribe anytime.
District construction staff updated the board on Edgewood facility renovations and presented bids for multiple phase 2 packages.
Staff said Phase 1 work is nearly complete: roof and masonry work were reported at roughly 99% completion for some buildings, and the main turnaround concrete and asphalt work was about 95% complete but delayed by recent poor weather. Window procurement is underway with installations targeted for February, and the main vestibule area was expected to close in by March. Staff cautioned that paving and some asphalt items may be delayed until spring weather allows.
Phase 2 bid results were presented for multiple packages returned on Dec. 20. Staff summarized bids for floor finishes (approx. $1.8 million), sprinkler systems (approx. $657,000), a general-construction (GC) package, ceiling/drywall (approx. $2,025,000), electrical/fire alarm (approx. $984,000) and others. The team reported most trades received three bids; the GC package had two bidders. Administrators recommended starting second-shift work (4 p.m. to midnight) in late January to late May and continuing through summer, noting the potential need to extend second shift into August to finish interior work while school is in session.
Committee members asked about lead-time risks for items such as auditorium seating and windows and the potential for discovering hidden asbestos during demolition. Staff said allowances were included in bid packages for latent conditions; if asbestos or other undisclosed conditions are found, the district may require supplemental approvals for remediation costs.
Why it matters: Edgewood is a major capital project for the district; schedule and lead-time risks affect student access to renovated facilities and the capital budget. Administrators recommended approving bid awards and a second-shift schedule to accelerate interior work, with allowances to cover potential unforeseen conditions.
No formal award votes were recorded in committee; staff said the bid packages would be presented for board action at an upcoming meeting.