A resident raised concerns that only one formal bid was received for a creek repair project and asked the town to convene Banning Engineering, town staff and the contractor for a preconstruction walk-through to ensure the scope covers creek-specific work.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
Resident Michael Swanson told the Town of Clayton council he was concerned about the single contract awarded for a creek project and requested a preconstruction meeting to review scope and linear-foot measurements.
Swanson said the town originally reached out to 10 excavation firms, three performed on-site visits and only one — Jammer Excavating — submitted a bid. He said original project documents were lengthy (104 pages) and that Banning Engineering later consolidated the paperwork; the only bid received was for $9,000. Swanson compared the $9,000 figure to previous creek work in the area (a 200-linear-foot job in 2019) and said he was worried items specific to creek work might have been omitted.
Swanson asked the town to provide him with the consolidated bid documents and recommended a meeting with Banning Engineering, the town’s representative (Pete) and Jammer Excavating’s superintendent before any work begins. Town staff indicated work could start toward the end of February and agreed to arrange a preconstruction walk-through.
No formal council action was recorded at the meeting; staff said they would provide Swanson a copy of the consolidated bidding documents and arrange the requested meeting.
Why it matters: A preconstruction meeting aims to reduce omissions in scope and prevent misunderstandings about site conditions and responsibilities during creek-related work.