Sunbury updates tree and sidewalk replacement: 84 panels replaced, 14 plantings deferred
Summary
City staff reported completion of tree removals, replacement of 84 concrete sidewalk panels and planting of most new trees under the Sunbury Sage project; 14 tree plantings were deferred due to nursery unavailability and four residents opted out of tree removal/sidewalk work.
Get email alerts on the Streets Trees Sidewalks topic
No spam. Unsubscribe anytime.
At the Jan. 8 Services Committee meeting staff summarized work completed under the Sunbury Sage tree and sidewalk project and next steps for remaining properties.
Staff reported that all designated trees were removed where planned, 84 concrete sidewalk panels were replaced, and most replacement trees were planted. Four property owners opted out of removal/repair (meaning their tree remained and their sidewalk was not repaired), and 14 tree plantings remain to be scheduled because stock was not available from the nursery this season. Staff said residents may opt in through 2025 to receive planting or repair work.
Why it matters: Sidewalk and tree work affects pedestrian safety, trip hazards and street tree canopy; the opt‑out process leaves open future enforcement or repair under the city’s sidewalk ordinance.
Key details: staff identified Aaron Noblett as instrumental in developing tree selection and planting standards and said residents who want to opt in should contact the city planner, Alyssa Graziano. Staff also recommended reviewing the city sidewalk ordinance to clarify enforcement mechanisms for long‑term maintenance and remediation on properties that opted out.
Ending: Staff said the project is largely complete and that the city will follow up on planting the remaining 14 trees and on potential ordinance clarifications this year.