Columbus Avenue streetscape work continues; utilities, short closures and traffic restrictions reported
Summary
Staff told the Sandusky Boards & Commissions that crews have installed new west-side water lines, are tying across the roadway as meter pits arrive, and installed storm utilities near Washington Street with temporary closures and 7 a.m.–5 p.m. work windows.
City staff updated the Sandusky Boards & Commissions on ongoing work for the Columbus Avenue streetscape project, describing water-line installations, storm-utility work, and temporary traffic restrictions.
Ms. Dukey (city staff) said crews have installed new water lines along the west side of Columbus Avenue and are beginning cross-street connections to serve east-side properties; connections to individual properties will wait until meter pit materials arrive so the city can coordinate switching services with each property…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat