Middle‑school addition on schedule and under budget, school officials say

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Louisa County officials reported construction progress on the middle-school addition, with $7.94 million spent (30.54% of budget) and 37.89% of the project complete; no change orders were reported for the board meeting packet.

School division staff showed board members progress photos of the middle‑school addition and reported the project is on schedule and on budget despite recent weather that postponed a planned concrete pour.

Facilities staff said contractors completed structural sheeting, began blockwork over the winter break and have set steel for the remaining second-floor work. The board packet shows $7,940,973.87 spent to date on the middle‑school project, representing 30.54% of the project budget, and a reported 37.89% physical completion. The facilities presenter told the board there were no change orders for the meeting.

Contractor work included interior prep, new door framing and helical piles for the auxiliary gym; staff said they expect no cost concerns at present and will continue to monitor weather-related schedule impacts. The board discussed scheduling a site tour once exterior conditions dry.

In the meeting packet the division included five payments to RRMM tied to project purchase orders; staff noted documentation for those payments was available in the board packet and subject to board questions. Board members thanked facilities staff for snow‑removal work and overall management of the project.