Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the School Construction topic
No spam. Unsubscribe anytime.
Facility committee reviews middle school contingency log; discusses solar infrastructure and federal reimbursement timing
Summary
The Waunakee Community School District Facility Committee reviewed the latest contingency log for the new middle school, discussed infrastructure left in place for future solar expansion, and updated the committee on the district's plan to pursue federal tax-credit reimbursement under programs tied to the Inflation Reduction Act.
Get email alerts on the School Construction topic
No spam. Unsubscribe anytime.
The Waunakee Community School District Facility Committee reviewed the middle school contingency log and discussed how solar-work and related reimbursements have been recorded in project accounting. District staff told the committee that the most recent contingency report reflects a reclassification of solar costs into the middle school project and that some federal reimbursement paperwork remains pending until the building is placed in service.
The update came from district staff during the committee meeting, who said the district asked its construction manager (Vogel) to include infrastructure that would allow future expansion of solar at the new middle school. Staff explained that some solar scope originally planned as a soft cost was moved into the capital project after a favorable bidding environment, and that additional electrical/infrastructure was being installed now to make a later expansion easier.
Why it matters: moving solar items into the project and installing expansion-ready infrastructure can reduce the disruption and cost of adding more solar later, but it also affects how costs appear in contingency and owner accounting. Committee members asked whether the treatment matched their earlier direction; staff said the change aligned with prior committee requests to preserve capacity for future solar expansion.
District staff also described steps to seek reimbursement tied to federal tax incentives and energy programs: legal and accounting work is under way, the district is working with WIFLI to file paperwork with the IRS, and the district intends to submit claims for other properties with completed energy work. Staff emphasized they must wait to file for the middle school until the building is placed in service. Staff also said the district’s outside legal counsel that had been assisting with those filings closed at the end of 2024 and that another legal/accounting partner is now handling outstanding items.
On contingency balances, staff pointed to columns in the contingency log that show owner-side and other contingency balances; staff told the committee the owner contingency had been reduced to roughly $70,000 (as reported in the log) and that other contingency columns had been updated to reflect the decision to park certain Inflation Reduction Act–related change orders in the owner portion while the district completes coordination with its accounting and legal partners.
No formal action was taken. Staff said they will continue to provide the monthly contingency log and will bring further updates as the middle school is placed in service and as reimbursement filings proceed.

