Solon Elementary construction ahead of schedule, under budget; 13th Avenue road costs pending

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

JA Dunn project manager told the Williston Basin School District No. 7 board that foundations are complete and the guaranteed maximum price leaves the project roughly $4.84 million under the $55 million budget; a city cost-share for 13th Avenue remains to be resolved.

JA Dunn project manager Ryan Anderson told the Williston Basin School District No. 7 board on Jan. 8 that construction of the new Solon Elementary School is progressing on schedule, foundations are complete and the project remains under the board’s $55 million budget.

Anderson said the contractor’s guaranteed maximum price (GMP) finalized at a special board meeting in December is $41,424,107. With conservative owner soft-cost estimates, he reported the project is approximately $4,841,000 under the $55 million budget. He identified a set of bid alternates still under…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans