Commission approves Greenheart Place preliminary plat with conditions amid concerns over plugged oil well and easement cleanup
Summary
The Planning Commission on Jan. 7 approved the Greenheart Place preliminary plat (SUB22-08) with conditions to address drainage, legacy easements and a plugged oil well shown on the site.
Get email alerts on the Preliminary Plat topic
No spam. Unsubscribe anytime.
The Stillwater Planning Commission on Jan. 7 approved the preliminary plat for Greenheart Place (formerly Quail Meadows) at East Lakeview Road (SUB22-08), subject to conditions addressing utility/drainage easement configuration, closure of legacy easements, and protections regarding a plugged oil well on the site.
Diana, planning staff, summarized changes since the previously approved plat: the developer added three residential lots in the southeast corner (raising single-family lots from 35 to 38), reshaped an outlot used for drainage (Outlot A) and eliminated an earlier Outlot B. Aaron Ferguson, project engineer with Bancroft Design, said sewer issues that previously delayed the project have been resolved, improvement plans have been submitted, and documentation showing a previously existing oil well has been provided to the city indicating it was plugged and that the operator provided shut-in paperwork to the Corporation Commission.
Commission discussion focused on three technical areas: drainage capacity and detention, utility and drainage easement separation, and the plugged oil well that lies partly within proposed lots. Ferguson said the detention analysis had been revised, was under city review, and still met the parameters of a previously accepted traffic-impact analysis. He acknowledged the plugged well documentation from the Oklahoma Corporation Commission and said the well was plugged "deep enough, so that we can build things on top of it and it's not an issue," though he did not confirm monitoring wells.
David Barth, development services, and Diana explained that drainage, erosion and any environmental issues would be reviewed during engineering and permitting; drainage easements and utility locations will affect where drainage facilities can be placed. Staff recommended separating utility easements from drainage easements where possible so utilities would not run through detention areas.
Some commissioners expressed concern about creating buildable lots directly over a plugged well and about how future homeowners would be made aware of the well's location. Staff said it could require a note on the final plat identifying the well location and that staff was continuing to work with the property owner on vacating or clarifying existing easements. The commission approved the preliminary plat with conditions requiring that utility and drainage easements be separated (so that a detention area is not subject to utility crossings), that existing easements be closed or clarified as appropriate prior to final plat, and that the well location be indicated and protected through plat notes or easements as necessary. The motion to approve with those conditions passed 5-0.
Staff noted final plat conditions and documentation (including easement vacation records and Corporation Commission closure documents) must be satisfied before final-plat acceptance and recording.