Mannock Road opening expected; stormwater fee, mud-on-streets and lead‑reporting work highlighted
Summary
The city engineer said Mannock Road should open following a culvert replacement, the stormwater utility ERU increased from $4.69 to $4.73 monthly for 2025, the city is exploring a developer 'mud bond' to reduce construction debris on streets, and a returning co‑op student will work on historic water main records for EPA lead reporting.
Get email alerts on the Infrastructure Stormwater topic
No spam. Unsubscribe anytime.
City engineer reported at the Jan. 6 North Ridgeville council meeting that Mannock Road is scheduled to open soon after a culvert replacement project, though warming weather is needed for final striping and seeding in tree-bond areas.
The engineer told council that several members had complained about mud on city streets from private developers. He said the city does not condone the condition and is considering options other communities use, such as a mud bond or deposit required before issuing building permits. He described citation or stop-work orders as time consuming and said the city wants alternatives to repeated enforcement actions.
Council received notice that the stormwater utility fee (ERU) for 2025 was adjusted using the Engineering News‑Record construction cost index (0.9% annual inflation). The engineer said that raised the ERU from $4.69 to $4.73 per month. The clerk also read a memo from City Project Engineer Eric Brown regarding the stormwater utility fee increase that took effect on Jan. 1, 2025.
The engineer announced a returning co‑op student, Aiden Appshire (civil engineering student, University of Toledo), would work through May reviewing historic water main records to support the city’s lead reporting work required by the U.S. Environmental Protection Agency.
No new permit regulations or specific timelines for a mud bond or deposit were adopted at the meeting; the engineer described the steps as items the city would like to address in the future.