Cowlitz County opens 11 bids for Tower Road water main and Juanita Way booster pump station

2090567 · January 8, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Cowlitz County clerk opened 11 bids for the Tower Road Water Main and Juanita Way Booster Pump Station (Project 2951). Clerk Kelly Grayson read bidder names and amounts; county staff noted several apparent transcription errors and said totals will be verified before award.

Kelly Grayson, clerk of the board for Cowlitz County, read 11 bids Wednesday for the Tower Road Water Main and Juanita Way Booster Pump Station project, project number 2951.

The bid opening, held at the county meeting, produced 11 submitted proposals. Grayson said the county will verify all totals; during the reading staff flagged several apparent transcription errors in the recorded dollar amounts that require clarification before any award decision.

Bids read aloud and totals as recorded in the meeting transcript included: Midway Underground LLC — $1,937,139.50; DeWitt Construction Incorporated — $1,555,950.70; Western United Civil Group LLC — $1,581,000,986.56 (apparent transcription error); KR Homes LLC — $2,863,929.96; North Cascade Excavating — $1,710,349.41; Swafford Excavating — $2,023,190.40 (a separate garbled amount of $2,000,000,230.40 also appears in the transcript and is unresolved); Grade Works Excavating LLC — $2,037,600 (followed in the transcript by $2,000,000,000,608.65, an apparent transcription error); CR Construction LLC — clerk noted the recorded number needs clarification and said the CR Construction figure exceeds $2,000,000; Advanced Excavating Specialists LLC — $1,799,597.03; Ratchi Inc. — $1,551,070.60; Topena Inc. — $1,560,357.57.

Grayson opened the item saying, "I'm opening the Tower Road, Water Main, and Juanita Way Booster Pump Station project, project number 2951." A meeting participant identified only as an operator indicated they could not confirm a bid amount for CR Construction during the reading.

The county did not take any award or contracting action at the meeting; Grayson concluded the reading by signaling the end of the bid opening. Cowlitz County staff will review and verify all submitted amounts and post the recommended action, if any, at a later date according to the county's procurement and contracting procedures.