Commissioners approve $37,450 change order for Clark Farm Road design, county engineer recommends added paving
Summary
The board approved a $37,450 design change order with Parker Engineering for Clark Farm Road, covering a drainage-easement plat ($3,250) and engineering to pave a short section of W.D. Peacock Road (design portion $34,200); the engineer and staff discussed estimated construction cost and T‑SPLOST funding.
Get email alerts on the Road Construction topic
No spam. Unsubscribe anytime.
The Bullock County Board of Commissioners unanimously approved a $37,450 change order with Parker Engineering for additional design services on the Clark Farm Road project.
Brad Deal, Bullock County engineer, told the board designers identified a low-lying area that holds water during rain events. The change order covers two elements: preparing a plat and adding a drainage easement to discharge stormwater to a nearby wetland (estimated $3,250), and engineering work related to upsizing cross-drain pipes under Clark Farm Road that creates a need to build up and pave an approximately 1,900-foot section of adjacent W.D. Peacock Road (design and permitting for wetlands, estimated $34,200). Deal said paving the short section of W.D. Peacock Road would reduce ongoing dirt-road maintenance and sand intrusion into the drainage structure.
Deal estimated, without bids, that paving the 1,900-foot section could cost roughly $350,000; he estimated construction for the entire Clark Farm Road project could be in the $2 million to $2.5 million range (his estimate centered near $2.25 million). Deal told commissioners the county currently has about $600,000 in T‑SPLOST funds budgeted this fiscal year for the project and roughly $500,000 planned next fiscal year, and cautioned that recent bid pricing suggests costs likely will exceed earlier budgets.
Commissioners had no public opposition; the board approved the single change-order motion to Parker Engineering by unanimous vote.
Deal said the design work will include required wetland permitting where applicable and that right-of-way negotiations could be needed to straighten a sharp curve on W.D. Peacock Road if property owners agree to a shift. No construction contract was awarded at the meeting; the action approved design-work funding only. The board did not set a construction schedule or commit construction dollars beyond the design change order approved at this meeting.