Summary

The Lawrence County Board of Commissioners entered two written notices into the record on Jan. 7: a Scott Township bridge replacement permit application to Pennsylvania DEP and a transmission-line filing affecting Pulaski Township.

At their Jan. 7 meeting, Lawrence County commissioners accepted two written communications and entered them into the public record: a December 19 letter from Taylor Engineering notifying the county of Scott Township’s intent to file for a Pennsylvania Department of Environmental Protection general permit (EUWGP11) for a bridge replacement on Hough Road, and a notice from FirstEnergy’s counsel that American Transmission Systems Inc. is filing for a 138 kV transmission-line loop to the Carroll substation that will affect portions of Mercer and Lawrence counties, including Pulaski Township in Lawrence County.

County staff said both documents have been forwarded to the county planning office for its records. Commissioners voted to accept the letters into the record; the roll-call votes recorded Commissioner Sonata, Commissioner Kennedy and Commissioner Vogler voting yes.

Why it matters: The DEP general-permit filing signals an upcoming bridge replacement project in Scott Township that will require permitting for work in or near water obstructions and encroachments. The transmission-line filing identifies a regional electric infrastructure project that includes work inside Lawrence County; planning and right-of-way considerations will proceed through the electric utility’s regulatory and local-permitting processes.

What’s next: Planning staff will review both filings as they proceed through state permitting and utility notification processes; the county did not take any additional action at the Jan. 7 meeting.