Park Norwalk staff reported progress this month on two multi-phase garage projects: structural concrete repairs at the Haviland Parking Deck and an aesthetic and lighting upgrade at the Yankee Doodle Garage.
Brian Candela, Park Norwalk staff, said the Haviland Deck concrete repairs began in late July and are now about 90% complete. Candela said the work was executed in phases to minimize disruption and that the contractor will finish concrete repairs and painting by November, pause for the winter and resume spring work (including waterproofing) when temperatures are favorable. He told the authority that the deck required “full-depth concrete repairs” including tendon repair at multiple locations.
The authority noted the project required a brief full closure the week before Labor Day at the businesses’ request to complete some work sooner, and that staff coordinated alternative parking options to reduce impacts on merchants.
Bridal Lutz, TMP staff, reported that work on the Yankee Doodle Garage began Sept. 30 with power washing and removal of fencing and signage to prepare the facade for painting. Lutz said power washing alone produced noticeable visual improvement and that painting of certain facades has been delayed by recent rain; the contractor is prioritizing the Burnell Side and River Street facades so they can be completed before cold weather limits painting.
Lutz also said Park Norwalk plans updated lighting in the Yankee Doodle Garage to improve nighttime comfort and safety for visitors and to encourage more long-term parking inside garages rather than on-street spaces. Staff emphasized the projects are paid from Park Norwalk’s fee revenue, not from general-tax dollars.
Authority members praised outreach to businesses and neighborhood groups done before and during the work, saying the engagement reduced disruption and helped secure local support.
Park Norwalk staff committed to continuing public updates and to present additional phasing details and timing as the contractors complete scheduled milestones.