City engineer reports progress on drainage, park and garage projects
Summary
Ryan Westra gave a status update to the Committee of the Whole on several public-works projects including completed sewer separation in the Anderson City drainage area, site work at Johnson Park, Atlantic Street garage entrance improvements and upcoming repair work at Firehouse Engine 2.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Ryan Westra provided the Committee of the Whole with a brief update on ongoing public-works projects and near-term work under way.
Westra reported the Anderson City drainage area sewer-separation project is complete except for minor punch-list items and said site work at Johnson Park is ongoing. He said entrance improvements at the Atlantic Street garage (Lot A) have been completed and that the contractor for repairs to the apparatus floor at Firehouse Engine 2 has applied for building permits and work should begin soon.
Other items mentioned included East Kennedy pump-station work and the annual resurfacing program. Westra noted concrete repairs are required on the apparatus floor at Firehouse Engine 2 and that building permits have been submitted by the contractor.
Westra’s update was brief and informational; no formal action or vote was recorded on these items in the transcript.