Rec center expansion awaits final drawings; cultural center portico delayed to Nov. 11; lighting project to start in December
Summary
Staff reported progress and delays on several capital projects: the recreation center expansion is pending 100% drawings, the cultural center portico finish was pushed to Nov. 11, Bob Marcello lighting is scheduled for early December, veterans park will go to bid soon, and a turf-fields grant decision is expected by Nov. 1.
Mister Pawlowski (staff member) provided the Recreation Advisory Board with updates on multiple capital projects during the Sept. 15 meeting.
Pawlowski said the recreation center expansion is moving forward but remains dependent on completion of 100% design drawings. He said the cultural center portico has been delayed because of material…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat