Lawmakers review $122.9M in public works recommendations; active projects total $1.9B
Summary
Committee reviewed Permanent Building Fund recommendations and Division of Public Works updates, including requests for specific capital projects and restored appropriations for deferred maintenance and prison construction.
Get email alerts on the Permanent Building Fund topic
No spam. Unsubscribe anytime.
The Joint Finance-Appropriations Committee reviewed the Permanent Building Fund, project status and Division of Public Works requests for fiscal 2026.
Legislative analyst Frances Lippett told the committee the total value of active public works projects is $1.9 billion and that 42 percent of funding for capital projects has been committed. She said the division typically expends 50 million to 70 million of its appropriation in a project's first year and explained the fund's statutory revenue sources, which include a $10 fee on income tax filings, portions of beer and cigarette taxes, lottery allocations and interest earnings.
The fiscal 2026 recommendation cited in the presentation totals $122,861,900 and includes six capital projects plus restoration of a repurposed appropriation and nearly $68.2 million for alterations, repairs and maintenance. Major items presented to the committee included:
- $6.5 million to expand the Department of Lands Ponderosa office, including added restrooms and improved reception security; - $5.56 million to connect utilities for a future Idaho National Guard readiness center in Bonneville County (readiness center expected to support up to 350 military personnel at peak occupancy); - $5.525 million addition to the previously appropriated funds for the Idaho State Police Lewiston District 2 facility after attempts to buy an existing building failed; - $2.5 million to add labs to the Micron Center for Materials Research at Boise State University; - $14 million for an Idaho State University life science complex (total estimated project cost $127,770,000 combining permanent building fund, agency funds and bonding); - $8 million for a joint military science and veterans assistance center at the University of Idaho.
Division of Public Works Administrator Dale Reynolds told the committee project timelines vary by delivery method and scale; some projects will take two to four years, and large construction efforts can take longer. Using the example of a women's prison project currently in design, Reynolds said the construction phase is expected to be roughly two and a half years once construction starts.
Deferred maintenance and repurposed funds were also discussed. Lippett described a restored appropriation of $12.5 million that had been repurposed in fiscal 2025 for other priorities; the recommendation would restore the funds and provide additional money for the ISU physician assistant facilities expansion. Lawmakers asked for lists showing projects that have not advanced within statutory or committee timelines; Lippett agreed to provide a project status list tied to the committee's reporting language.
Why it matters: the permanent building fund finances multi‑year capital and maintenance projects across state agencies and institutions; the committee's funding decisions shape which projects move forward and which funds are repurposed.
Next steps: committee members requested targeted follow-up about projects that have not advanced and about the four‑year reporting provision included in last year's budget language.