The county board approved PC 23-25, a three-segment 69-kilovolt transmission line reroute proposed by Great River Energy that county planners and the planning commission recommended for approval after staff reported no concerns.
Planning staff described PC 23-25 as a request from Great River Energy to reroute a 69-kilovolt transmission line in three segments across McPherson and Decoria townships. The reroute includes approximately 0.5 miles connecting County Road 174 and Township Road 600 and a roughly 2.5-mile segment in the County Road 177 right-of-way in Decoria Township;…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans