Ashland Middle School roof replacement set for July; AHS modernization and seismic work advancing
Summary
District bond program staff reported contractors will be on site in July to remove and replace the Ashland Middle School roof and provided progress updates on Ashland High School modernization and science seismic projects, including chiller installation, shear wall work, and courtyard reconstruction.
Get email alerts on the Facilities And Maintenance topic
No spam. Unsubscribe anytime.
Bond program staff gave the board an update at the June 12 meeting on ongoing construction projects funded through district bonds, including a commitment to roof replacement work at Ashland Middle School and continuing progress at Ashland High School.
Ashland Middle School roof: Staff reported that contractor Adroit and its subcontractors are committed to be on-site in July to remove and replace the roof and address known mechanical and penetration work that have contributed to leaks since project completion. Staff said they expect the work to continue through July and that they are optimistic the roof will no longer be a source of recurring leaks going into the next school year.
Ashland High School modernization and science seismic upgrade: At the AHS modernization project staff said the remaining construction tasks include installing chiller electrical gear required to make the gymnasium chiller functional; electricians were scheduled to begin that installation and then move to testing and commissioning with completion anticipated by August. For the science seismic project staff reported interior shear-wall installation in the library is complete, contractors are working on finish items such as drywall, ceiling tile and painting, and some classroom work is ahead of schedule and expected to be done by July. Exterior work includes sheathing and siding installation, placement of structural steel components and work on the quad area; paver installation at the courtyard is expected to begin late in the month.
Staff noted that phases requiring early access to building areas were coordinated with teachers and students and that facilities and school staff accommodated early access so contractors could make rapid progress. The board thanked staff for the update and had no additional questions.
Sources and names: The update was presented by bond program staff including Rebecca Buardson and Josh (last name not specified in the record). Project contractor names mentioned in discussion included Adroit and Serta (in the context of confirming repair work).