Council hears updates on Christopher Columbus Drive corridor, DOT grants and traffic-code changes
Summary
City staff described multiple transportation grants and projects for Christopher Columbus Drive, including coordinating sewer/water work with JCMUA, grant extensions with NJDOT, multiway-stop code amendments, and pedestrian/bike safety improvements.
Get email alerts on the Transportation Infrastructure topic
No spam. Unsubscribe anytime.
Drew Banghart, representing the Jersey City Department of Infrastructure, briefed the council on a package of transportation items including grant awards, a requested grant extension, and planned streetscape and safety improvements along the Christopher Columbus Drive corridor.
Banghart said the city is seeking a six-month extension on a New Jersey Department of Transportation (NJDOT) grant for Christopher Columbus Drive to coordinate work with the Jersey City Municipal Utilities Authority (JCMUA). He said the extension will allow the city to align above-ground roadway, sidewalk and curb work with the MUA’s water-and-sewer pipe installations so the city avoids redoing pavement after underground utility work.
Banghart identified three related resolutions: Resolution 25-637 (authorizing acceptance of a NJTPA grant to fund positions in the city’s transportation planning group and work on a transportation master plan), Resolution 25-638 (requesting a six-month extension of the NJDOT grant for Christopher Columbus Drive), and Resolution 25-639 (acceptance of 2024 DOT funding for the Christopher Columbus Drive corridor work).
On design elements, Banghart said the project will add curb bump-outs to reduce pedestrian crossing distances, install wider sidewalks where they are missing, and implement a mix of ground-level and raised bicycle-lane treatments similar to parts of Cole Street. He said city staff are finalizing designs and expect to start work next year, coordinating with the JCMUA’s schedule and its pursuit of low-interest funding.
Council members asked for more detail about timing; Banghart said the MUA is working to secure funding and the city aims to “get started next year.” Council members also raised whether curb bump-outs would be at all intersections; Banghart replied the design is still being finalized and would vary by location.
The transcript records staff presentations and questions but does not include recorded roll-call votes or final adopted language for the resolutions in the provided excerpt.
(Ending) City staff emphasized coordination with the JCMUA and the value of aligning utility and roadway work to avoid rework and preserve federal/state funds; council members requested follow-up on design details and timing.