Bridal Road project ahead of original pace, city engineer says; $6.2 million job to finish next summer (weather permitting)
Summary
City engineering staff reported progress on a $6.2 million Bridal Road reconstruction project, saying the contractor added crews and weekend work in an effort to cut the schedule from 18 months to 12 months; utility conflicts and weather have caused intermittent delays.
JP Terrazas, Mission’s city engineer, updated the City Council on the Bridal Road reconstruction project during the Oct. 14 meeting, saying construction began Aug. 11, 2025 and the contractor is working extended hours and weekends to shorten the original 18‑month schedule to 12 months.
Why it matters: the corridor serves schools, a Walmart site and other businesses and has experienced heavy traffic. Terrazas told the council the work includes full excavation of the west side, drainage and inlet installation, sidewalk work, and paving in sections to maintain access for adjacent…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat