Board moves to prioritize Springstead track resurfacing; Central track planning estimated at $1.5 million
Summary
Staff told the board the Springstead rubber track will be resurfaced after a field project; the deeper Central track rebuild was estimated at about $1.5 million and will move into planning and bidding under half-cent funding.
Get email alerts on the Facilities Track Resurfacing topic
No spam. Unsubscribe anytime.
Board members discussed resurfacing projects for Springstead High School and the district's Central track during the Oct. 7 informal meeting, and staff said they will coordinate the work with ongoing field renovations.
A facilities staff member told the board the Springstead rubber surface can be resurfaced without replacing the base and that the resurfacing will be scheduled to follow the current field project; the work will use a separate contract from the field contractor. "We'll do that when we do the, or right after that field is finished," the facilities staff member said.
By contrast, the Central track requires a full base rebuild. The facilities staff member gave an estimated cost of about $1,500,000 to tear up the base, rebuild it and resurface the track. That project will move into planning and bidding this year, the staff member said, and both projects were described as being on the list funded by the district's half-cent sales-tax program.
Board members asked whether major renovations at Springstead — including building front reconfigurations and roof work — would force redoing the track; staff replied the track timing was coordinated so the field and underlying work would not be undone by other building projects. The staff member said there is limited space for retention ponds at Springstead, which factored into the need to upgrade the field.
No formal contract awards or budget votes occurred during the informal meeting. The board's direction was administrative: facilities will put Springstead resurfacing in the queue and proceed with planning for the Central track, with further cost and scheduling details to come to the board as bids and plans are developed.
Ending: Facilities staff will return with bidding timelines and refined cost estimates; the board did not approve construction contracts at this meeting.