Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Infrastructure Sewer Projects topic

No spam. Unsubscribe anytime.

Commissioners set Oct. 10 deadline for sewer easements; temporary-fencing cost flagged

5880515 · October 2, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Planning staff told the commission temporary easements are due Oct. 10 to allow contractor access for the sewer connection project; contractor estimated temporary fencing would cost about $500–$750 per property and a worst-case total just under $50,000 if every property requested it.

Amanda Web, planning director, updated the commission on the wastewater connection project and said staff have begun a final push to collect temporary and permanent easements from property owners. Staff set a revised deadline of Oct. 10 for remaining temporary easements, and said staff will meet owners in the field and provide notary services if needed.

The nut graf: the county needs temporary access to private property to decommission septic tanks and install sewer connections; several property owners requested temporary fencing while their regular fences are removed for a few days during construction, and the additional cost is not in the current project budget.

Web said most easements are temporary; a handful still require permanent documents and that staff had accommodated minor contract language changes when requested. "If they don't have time to come to us . . . we will come to them," Web said, describing county staff offers to meet residents on-site with documents and a notary.

Contractor BG estimated temporary fencing would cost roughly $500–$750 per property; Amanda and county staff presented a worst-case figure of about $48,000 if every property in the district requested a temporary fence. Web and Jacob Hanson, county counselor, said that cost is not currently included in the project budget and that commissioners could decide whether to add a contingency or provide temporary fencing on a case-by-case basis.

Commissioner Fokie volunteered to assist with door-to-door outreach to property owners who had not returned easements. Staff said contractors will publish a week-by-week schedule and notify property owners at least a week or two in advance of work on individual properties; typical on-site work is expected to last only a few days per property absent unusual site conditions.

Ending: Staff agreed to return with a count of properties that have existing fences and an updated estimate for temporary-fencing requests so the commission can decide whether to authorize a not-to-exceed contingency for that line item.